Survey work for the Three Forks Church Road Water Project has been completed, and design development is currently underway at approximately 50% completion. It is anticipated that design efforts will reach a point for submission to the appropriate permitting agencies by May 7th and that permit reviews and approvals will be ready for bid advertisement in the late summer of 2025.